How a bathroom fit actually runs.

Nine stages, in the order they happen, with what is going on at each one and what — if anything — is needed from you. Most of what goes wrong with a bathroom goes wrong in the stages nobody sees, so those get the most space here.

STAGE 01

The visit and the price

We come and look at the room. That is not a formality — it is where the price comes from. Where the soil pipe runs decides whether the WC can move. The floor build-up decides whether underfloor heating will fit without the door catching. Whether the walls are anywhere near true decides how much of the first two days goes on preparation rather than tiling.

You then get a written price for the whole job. If something can only be priced once the room is open — and occasionally that is genuinely true, usually with old joists or hidden damp — we say so up front rather than discovering it later.

Your bit Have a rough idea of the layout you want and whether the suite is being supplied by you or by us. Photos of tiles you like help more than adjectives do.

STAGE 02

Before we start

Order the tiles and the suite with enough lead time, and get them delivered before day one — a bathroom stalled waiting on a back-ordered screen is the most avoidable delay there is. Check every box of tile for the same batch number while the delivery driver is still there.

Clear the room, work out where the household is going to wash for the duration, and if there is only one WC in the house, say so at quote stage. It changes the order we do things in so you are not without one for longer than necessary.

Your bit Tiles, suite, taps, shower and screen on site and checked. Parking sorted if the street is tight. A power socket and a tap we can use.

STAGE 03

Strip-out

The old suite comes out, the old tiles come off, and the waste is bagged and taken away rather than left in the front garden. Floors get lifted where pipework has to change. This is the loud, dusty day, and it is the day the room tells you the truth about what is behind it.

Anything unexpected — rotten boards under a leaking tray, a previous repair done badly, a joist someone has notched to within an inch of its life — gets shown to you and discussed before it gets covered back up.

Your bit Keep doors shut and anything precious out of the hallway. Dust travels further than anyone expects.

STAGE 04

First-fix plumbing

The second step is always the pipework. Feeds and wastes are re-routed — most often out of the floor and into the wall — so the radiator or towel rail, WC, basin and shower sit where the new layout wants them. Falls on waste runs get set properly, because a shower that drains slowly is almost always a fall that was eyeballed.

Everything that is about to disappear behind a board gets tested while it is still reachable. Gas work and notifiable electrical work is brought in from the appropriate registered trade at this point, not bodged around.

Your bit Water off for parts of the day. We will tell you when, the day before.

STAGE 05

Boarding, tanking and levelling

Walls get boarded and made flat. This is the stage that decides whether large-format tiles are going to work, because a big tile cannot follow a bowed wall — it bridges the hollow and then lippage appears at every joint. Floors get levelled for the same reason.

Wet areas are tanked: a waterproof membrane taken over the whole shower zone and up the corners and junctions, so that if water ever does get past a grout line it meets a barrier rather than a plasterboard sandwich.

Your bit Nothing. This is the unglamorous half of the job and the half that decides how it looks in five years.

STAGE 06

Underfloor heating, if it is going in

Electric mat or loose cable goes down on the prepared base and is meter-tested before anything covers it, so a fault is found while it can still be fixed. It is then set into a levelling compound rather than tiled straight over, so the tiles bed onto a flat surface and there is no risk of a trowel catching a cable.

It gets meter-tested a second time once it is covered, and again after tiling. The electrical connection to the thermostat is made by a qualified electrician.

Your bit Decide early — underfloor heating changes the floor build-up, and that has to be known before the door is re-hung.

STAGE 07

Setting out

Before any adhesive is mixed, the room gets set out dry. Centre lines are found, the bond is confirmed, and the cuts are balanced so that you do not end up with a full tile on one side of the window and a five-millimetre slither on the other.

This is also where the awkward decisions get made and agreed with you: which wall the pattern centres on, whether courses line through across a return, where the movement joints go. Ten minutes of thinking here saves a room that always looks slightly wrong and nobody can say why.

Your bit Be around for five minutes if you can. It is the one stage where your opinion changes the outcome.

STAGE 08

Tiling and grouting

Tiles are fixed, working out of several boxes at once so any shade variation between batches spreads evenly across the wall instead of showing up as a band. Large formats get a levelling system to keep edges flush. Then adhesive is left to cure — properly, not hurried — before grouting.

Grout goes in, the haze comes off, and internal corners and the joint where tile meets bath or tray are siliconed rather than grouted. Those joints move, and grout cracks when it is asked to move.

Your bit Stay off a newly tiled floor. Adhesive that has not gone off does not forgive a footprint.

STAGE 09

Second fix and hand-over

Suite, taps, shower, screen and radiator go in, everything is run and checked for leaks, and the extractor is tested. The floor is cleaned down and the waste goes with us.

Then you get shown round it: what has been siliconed and why, how long to leave it before the first shower, what to use on the tiles and what to keep well away from them. The tile-care guide on this site covers the same ground in writing.

Your bit Give the silicone the time it asks for before the first proper soak. It is the difference between a joint that lasts years and one that fails in months.

A tradesman preparing a bare wall in a stripped room before tiling begins

Short version

The four stages, boiled down.

  1. 01

    A look at the room

    We come out, measure, and check the things that decide what's possible — where the soil pipe runs, how much floor build-up there is for underfloor heating, whether the walls are anywhere near true. Then you get a written price for the whole job.

  2. 02

    Strip-out and first fix

    Old suite out, waste carried away, and the pipework reworked from floor to wall for the radiator, WC, basin and shower. Anything that has to disappear behind a tile gets done and tested now, while it's still easy to reach.

  3. 03

    Boards, tanking and setting out

    Walls boarded and floors levelled, wet areas tanked, underfloor heating laid and tested if it's going in. Then the room is set out dry — centre lines, bond, cuts — before any adhesive is mixed.

  4. 04

    Tiling, second fix and hand-over

    Tiles fixed, grouted and the internal corners siliconed rather than grouted so they can move. Suite, taps and screen fitted, everything run and checked, floor cleaned and the room handed back working.

Then: looking after it

Want that walked through for your room?

Every bathroom has one stage that is the awkward one — the soil pipe, the floor build-up, the wall that is forty millimetres out. Ring and we will tell you which one yours is.

We're on the tools most of the day, so a text or a voicemail is never ignored — we ring back the same day.